636.184.876 EU funds in HUF million Pacino area water management starts at the beginning of March. Framework of development for all streets in the town Bodrogköz the government aims to establish an overall settlement 25,9 km of inland- and storm water drainage system.
Pácin Township inner area and the hinterland threatening, related to the outskirts of water to settle out in relation to the implementation of the plan Vasarhelyi, flood affected areas as tározással. In urban drainage of surface water drainage to solve without damage.
Successfully applied within the framework of the Operational Programme of North-Hungarian Széchenyi Plan EU allowance, which 100 %-obtained in addition to an aid intensity!
Thanks to several years of planning and preparatory work 2013 At the end of our village started to address the problem of long-standing urban water management. He stood in project management and in the second, successful procurement procedure chosen for the task suitable contractor.
Description of the project:
The Municipality collects rainwater in large part to the host channel Pacino, Belsőági the channel, Mogyorós worth and operating channels. The channels of collected rain water drains leading to the main reception Tiszakarádi.
Smaller part of the municipality is the recipient collects rainwater Felsőberecki main channel, Karcsa the Pap-worth and the Lake.
The inner area of town due to the low-lying topography and geological conditions can, marshy, wetlands are found. In these areas, farming is not done, Depending on the rainfall water borítottságú periodic function as habitats. These low-lying public health financially favored, soiled areas a small part of the settlement of precipitation waters are still and will be the host after area water management.
A significant part of the proposed settlement will be covert channels beck earth ditch and simple earthen trench, which led to the aforementioned recipients gathered in an urban rain waters, so will be terminated on the infiltration characteristics.
The exception is the katlanszerű Salt Lake street, which gathered the rainwater can not drive because of the terrain recipient. Because of the narrow street and the cross-section a few years ago built sewers in the street just placed an infiltration trench. The town on the main street just closed channel is designed, a relatively short length.
Northern part of the village collected rainfall water 4 at the sewage treatment ÉMVIZIG introduced in. The open channel inlet ducts are made, rézsűjét the host and the channel bottom 5-5 feet in length provided with kőszórással, and the connecting trench min. 5 meters length provided with protection kőszórásos.
Technical content of the project:
Indicators:
- Total channel length: 25.960 fm
- earth pit 6.098 fm;
- paved ditch 16.564 fm;
- closed channel 763 fm;
- culvert 2.535 fm;
Other tasks planned:
- retaining walls and steel prohibitive 1141 pc;
- inspection chambers 5 db 7 db,
- gully pit 8 pc;
- közműkiváltás – gas, water, sewage, electricity – 88 pc
Implementer:
Construction ZEMPLÉN STONE eastern Hungary General Contractor and Mining
Limited liability company,
Based in: 4914 Olcsvaapáti, György út 31.
Company registration number: 15-09-079847
Tax Number: 12523326-2-15
Representative: Toldi Executive
Execution time: 2013.12.16 – 2014.09.12
Implementation date for the project: 2014.October 31.
EU aid is a good place: safe, modern environment by reducing the threat of public harm caused by domestic and stormwater.
Emphasized, that the investment volume will contribute to the reduction of unemployment in the investment period. By all means we want to improve the population's living conditions Pácin, therefore, the subsequent acquisition of new resources we will continue to improve municipal infrastructure.
Pácin, 2014. március 5.
Laszlo Majoros mayor